Conversion of The Whitehouse, Grade II Listed Building
to form a Spa Management Training Centre.
Client
Warwickshire College
Architect
Hitchman Stone Partnership
Contractor
GAJ Construction Ltd
Date Completed
March 2005
Works Cost Value
£1,250,000.00
Key Services
Cost Planning and Two Stage Construction Management Contract
Case History
No scheme design or condition survey had been undertaken at the stage
when the initial cost plan was required for funding submission. Using
historic data the estimate was prepared in the sum of £1,250,000.00.
The project was required to be completed within 12 months
of the our appointment and we advised the College to adopt a construction
management form of procurement on a two stage basis in order for the investigation
and remedial work to be commenced whilst the designs for the remodelling
were completed.
The client was advised of the risks versus benefits of
this form of procurement.
The centre opened in April 2005 on budget.
|
      |